Wednesday, January 28, 2015

Street Repairs Delayed Due to Rising Costs of Materials Johnny Heath Corpus Christi News Blog

Discouraging news at council regarding bond street improvement projects. Costs have increased to almost $30 Million over budget. Those projects, which come from the last several bonds approved by voters since 2004, include all the streets that meet at the Six Points area.Those costs of some $28 Million are the result of increases in labor costs as well as material costs. For example, the costs of concrete alone has risen more than 20% in the last six months. But the city's department of publi...



from KIII TV3 - News http://ift.tt/1EqXyZ5

via IFTTT Johnny Heath Corpus Christi News Blog,#DecodeDC ,#JohnnyHeath ,#CorpusChristi, #JohnnyHeathCorpusChristi ,http://ift.tt/1tyT6NC ,http://ift.tt/1rpUPKU